618 Carnarvon Construction Updates

• Level 32 Complete
• Level 33 Slab Complete
• Mock-up suite Complete

WORK IN PROGRESS

Precast 90% Complete
Level33 Columns 85% Complete
Windows & Water Proofing 70% Complete

Level 32 Complete
Level 33 in Progress
Blockwork, Steel Stud in Progress

Upcoming Schedule

  • Complete Kitchen Manufacturing for levels 5-7
  • Complete Mechanical & Machine Room Slab
  • Complete Steel Stud, Insulation, Boarding, Water Proofing and Window Installations