Updates

THE LATEST UPDATE

618 Carnarvon Construction Updates

• Parking Level 3 complete
• Slab on Grade work up to P4 complete
• Underground drainage for P4 complete

WORK IN PROGRESS

Parking Level 3 Complete
Slab on Grade Work up to P4 Complete
Underground Drainage for P4 Complete
Underground Services for P5 Complete

P2 Columns 75% Complete
P1 Decking 50% Complete
Concrete Rendering for Parking Arcade Started

Upcoming Schedule

  • Slab on Grade concrete pouring for P1 and P2
  • Start building walls for P1
  • Complete vertical elements for P1 and P2